Annex III. Background to the BSAPP

Step 1 Getting Organised.

PEnA was selected as the national focal point and national executing agency. A Project Manager, team of environmental and agricultural specialist and support staff within PEnA were assigned to the project. A 12 member Steering Committee comprised of representatives from various government ministries, NGOs and universities was established on 20 November 1997. The role of the Steering Committee was to:

Advise and assist the Project Manager;

Review the reports of the Technical Working group; and

Act as a forum for discussion and achieving consensus on the main components of the BSAPP.

The Project Manager has been in regular contact with the Steering Committee, they have been invited to all workshops and have convened twice during the life of the project. It is anticipated that the Steering Committee will convene again in mid-November 1998 to discuss the draft BSAPP.

Table 40: BSAPP Methodology and Reporting

Planning Step

Reporting Process

1. Getting organised

Relates to all reports

2. Data gathering and assessment

Country Study

3. Option identification and analysis

Situation Analysis

4. National strategy

National Strategy

5. National action plan

Action Plan

6. BSAPP implementation

Iterative process, monitoring and evaluation reports will loop back into

7. BSAPP monitoring, evaluation and reporting

National Biodiversity Strategy and Action Plan

Source: Adapted from WRI et al, 1995 and GEF/ UNDP, 1998.

Wide representation on the Steering Committee was sought in order to maximise the input and viewpoints incorporated in the BSAPP. Moreover, as PEnA is intending to submit the BSAPP to the PA for approval and incorporation into national planning; it was felt that the more Ministries that have an opportunity for early input, the more quickly it will be adopted by the PA. The names, title and agency of the members of the Steering Committee are given below:

Table 41: Steering Committee Members and Agency

Steering Committee Member

Title and Agency

 

Dr Sufian Sultan

Head, PEnA (Steering Committee Chair)

Dr. Yousef Abu-Safia

Head of Natural Resources Committee in the Palestinian Legislative Council & Current Minister of Environment.

Mr Ali Shaath

Deputy Minister, MOPIC

Mr Sami Mussallam

Director General, President’s Office

Dr Kamal Qubba’h

Legal Advisor to President of PA

Dr Jad Isaac

Director General, ARIJ

Mr Musa Abu-Gharbiah

Director General, Palestinian Water Authority

Mr Abdallah Abdallah

Director, Palestinian Geographic Center

Mr Adel Barageeth

Director General Rangelands and Forestry, MOA

Dr Adimar Es-Ghier

Head of Department of Biology, Birzeit University

Dr Jawad Wadi

Administrative Vice Chancellor, Al-Azhar University

Mr Ibrahim Jadallah

Director General, Ministry of Tourism

Step 2 Data Gathering and Assessment

Within the first month of the project six Palestinian consultants were contracted to produce background reports including recommendations on various aspects of biodiversity in Palestine. These six specialist along with the Project Manger are referred to as the Technical Working Group. The specialist, agency and subject matter are named below:

Table 42: Technical Working Group

Specialist and Agency

Subject Matter

 

Mr Imad Atrash, CPNP Coordinator

Terrestrial biodiversity - fauna

Mr Adel Breighieth, Director General Rangelands and Forestry, MOA

Terrestrial biodiversity - flora

Ms Nadia El Khodary, Consultant to PEnA, Dutch Environmental Planning Project

Marine and freshwater biodiversity

Dr Kamal Qubba’h, Legal Advisor to President

Legal issues of biodiversity

Dr Shahir Hijjeh, Al Quds Open University

Socio-economic issues of biodiversity

Mr Younis Sbeith, Conslutant to PEnA, ICARDA Agro-biodiversity project

Agro-biodiversity

Work began in earnest on 8 December 1997 with the first working group meeting. Below is the list of meetings and workshops that highlighted the progress of the BSAPP.

Table 43: BSAPP Meetings and Workshops

Meeting/ Workshop/ Agenda

 

Participants

Date

1st Instructional workshop/ 1st steering committee meeting.

Inception workshop – introduced participants to the BSAPP and provided TWG with TOR.

Steering Committee, TWG

8 Dec/ 97

1st Planning team meeting.

Established time frame, reviewed Terrestrial – flora progress.

TWG, PEnA,

2 Jan/ 98

2nd Planning team meeting.

Review timeframe, reviewed marine and freshwater, socio-economic and legal progress.

TWG

20 Jan/ 98

3rd Planning team meeting.

Discuss preparatory steps and reports to be presented at the 1St national workshop.

TWG

21 Feb/ 98

2nd Steering committee meeting.

Review of TWG workplan and reporting format.

Steering Committee, IUCN, Project Manager

24 Feb/98

2nd Instructional workshop.

Discussed TWG recommendation responsibilities and format.

TWG

27 Feb/ 98

1st National workshop.

Inform broadly the purpose of the BSAPP; identify potential conflicts between resource use and conservation; identify priority options for conservation; and to encourage discussion among stakeholders

PEnA, Government Officials, NGOs, Universities and other stakeholders

12 Mar/ 98

1st Provincial workshop.

Inform broadly the purpose of the BSAPP; identify potential conflicts between resource use and conservation; identify priority options for conservation; and to encourage discussion among stakeholders

PEnA, District Government Officials, NGOs, Universities and other stakeholders

15 Apr/ 98

2nd Provincial workshop.

Inform broadly the purpose of the BSAPP; identify potential conflicts between resource use and conservation; identify priority options for conservation; and to encourage discussion among stakeholders

PEnA, District Government Officials, NGOs, Universities and other stakeholders

30 Apr/ 98

4th Planning team meeting.

Reviewed TWG reports and discussed gaps.

TWG

28 May/ 98

BSAPP Arab regional workshop.

Provide a forum for countries exchange ideas, lessons learned and biodiversity planning experiences with GEF/ UNDP, UNEP and IUCN resource persons.

National Project Managers from PA, Yemen, Tunisia, Lebanon, Djibouti, Sudan, Jordan, Syria, Algeria and Oman.

11-13 June/ 98

Task force inception workshop.

Establish task force workplan

Dr. Sultan, Task force

29 Sep/ 98

Task force-drafting workshop.

Finalise draft BSAPP

Task force

21-24 Oct/ 98

Final workshop.

Finalise BSAPP

Task force, TWG, Steering Committee

16 Nov/ 98

Step 3, 4 and 5

In late September 1998, PEnA established a BSAPP Task Force comprised of the Project Manager, the TWG, ARIJ and 3 outside consultants. The Task Force’s role was to finalise the TWG reports including recommendations and complete the draft BSAPP.

Step 6 and 7

The implementation and monitoring and evaluation will begin after the approval of the BSAPP.